World Heritage Site: The Forth Bridge
Publication Year: 2013
Publication Type: Article
Publication Identifier: WHE0C29ECCF46
Summary
Structural deficiencies in the Forth Road Bridge's approach viaducts, exacerbated by corrosion-induced bearing lock-up and chloride-contaminated concrete deterioration, necessitated a comprehensive bearing replacement project. The study highlights how these issues altered the bridge's articulation, compounding structural weaknesses. It provides a detailed account of the design and implementation of temporary works to maintain bridge stability during jacking operations while outlining modifications to facilitate bearing replacements. This case study offers valuable insights into the challenges of large-scale infrastructure maintenance in heritage structures.
Citation
Colford, B., Chiarello, M., Hendy, C. R., Pouya, H., Sandberg, J., & Smout, P. (2014). Bearing replacements for Forth Road Bridge approach viaducts. Proceedings of the Institution of Civil Engineers - Bridge Engineering, 167(3), 170–182. https://doi.org/10.1680/bren.11.00051
You are here:
World Heritage Explorer > World Heritage Research > Publications > Bearing replacements for Forth Road Bridge approach viaducts